Energy News Weekly Digest – June 03-06, 2025

Guy clamps and smart tech expanding Colombia’s grid

Colombian power grid expansion

Colombia issues a tender for a 230 kV substation in Sopo and associated lines. The winner will get a 25-year concession to design, build, operate, and maintain. The project cost is estimated at $3.5 billion, including HVDC transmission for 3 GW of renewables.

There is integration of HVDC lines, SCADA, AMI, and remote fault detection systems. Smart meters enable real-time demand monitoring and demand-response strategies.

Guy clamps anchor guy wires, stabilize poles and towers, and counteract wind, seismic shifts, and uneven soil. They provide even load distribution, adjustable tension, faster installation, and corrosion-resistant quality.

There is also the development of batteries, flow batteries, and pumped hydro to buffer variable renewables. FACTS devices enhance voltage control and power flow management.

Small-scale solar and wind plus storage and smart control are ideal for rural electrification and grid resilience.

Efforts such as integrating 3 GW of renewables, modernizing infrastructure, and supporting equitable energy access help align with Colombia’s national goals.

Read More

#PowerInfrastructure #SmartGrid #GuyClamps #EnergyStorage #Microgrids

C-SPAN clamps down on speeding up wind energy in Colombia.

Wind energy development efforts

Global energy giants Enel and EDP Renewables have exited wind power projects in La Guajira, citing regulatory instability and local tensions.

Colombia’s energy transmission network has failed to keep up with renewable project timelines. La Guajira’s isolation from the national grid makes interconnection logistically and financially difficult. The delay in grid development is a primary bottleneck in scaling wind capacity.

C-SPAN clamps are crucial components in both the electrical and structural systems of wind energy facilities. They secure overhead cables, withstand high tension, offer vibration dampening, and provide corrosion resistance.

Poor supply chain logistics and import delays for specialized clamps have slowed construction. Lack of standardized specs has led to project design inconsistencies.

Indigenous Wayuu communities report poor consultation and environmental concerns. Some may see the wind farms as opportunities and others as threats to ancestral lands and resources.

Read More

#ColombiaWindEnergy #Renewables #CSpanClamps #InfrastructureDelays #GridConnection #EnergyTransition

Cable suspension bolts powering Colombia’s wind future

Wind turbine development efforts

Colombia’s rugged zones demand high-quality components like cable suspension bolts to help transmission towers withstand seismic and wind stress.

The 88 km, 220 kV backbone is vital for Colombia’s wind farm and guarantees transmission across challenging terrain.

Cable suspension bolts anchor medium- and high-voltage cables from wind turbines to transmission lines. They counter wind and ensure safe and reliable electricity transmission.

Wind turbine lift assistance is used in staging, installation, and erection supports for large turbines. They also reinforce platforms and HV equipment to mitigate vibrations and maintain structural integrity.

Development of wind projects contributes to fossil fuel displacement, which aids the Paris Agreement goals.

The use of cable suspension bolts provides safe, durable power infrastructure. They also serve in wind and solar to support the ongoing rollout.  

Read More

#RenewableEnergy #GridInfrastructure #WindEnergy #PowerTransmission #CleanTech